Step No. |
Project Plan |
Step Status |
Start Date |
Completion Date |
12 |
Approved Standard
|
Published |
10/20/08 |
11/20/08 |
11 |
Notice of Intent to Adopt Draft |
Completed |
6/6/08 |
7/7/08 |
10 |
Draft Standard for Ballot
|
Completed |
3/13/08 |
4/24/08 |
9 |
User Comment Draft Comment Resolution
UCD Comment and Resolution Draft Summary
|
Completed |
2/3/08 |
4/24/08 |
8 |
User Comment Draft Standard
|
Completed |
11/1/07 |
1/2/08 |
7 |
Design Content - Committee Working Draft 3
Note there was an “interim draft 3”, which was replaced by the drafts identified below (hence the numbering)
|
Completed |
7/27/07 |
10/8/07 |
6 |
Design Content - Committee Working Draft 2
- TMDD/ MSETMCC Vol. 1, Draft 2.
This Draft contains User Needs, Requirements, and the Needs to Requirements Matrix, NTRM). This draft of the complete Vol. 1 contains a complete NRTM (minus the column on Additional Project Requirements, which we have not yet entered into the traceability tool so it can be included in the matrix).
- TMDD/ MSETMCC Vol. 2- Design, Draft 2. This draft contains definition of dialogs, messages, data frames, and data elements to support the requirements of Vol. 1. This draft contains an initial Requirements Traceability Matrix (RTM) tracing requirements to design.
|
Completed |
6/13/07 |
7/09/07 |
5
|
Design Content - Committee Working Draft 1
|
Completed |
4/10/07 |
5/21/07 |
4
|
Standards Requirements Specifications
|
Completed |
1/10/07 |
4/26/07 |
3
|
Concept of operations – User Needs
|
Completed |
8/31/06 |
1/25/07 |
2
|
Systems Engineering Management Plan
|
Completed |
6/1/06 |
8/15/06 |
1 |
Project Management Plan
|
Completed |
6/1/06 |
8/15/06 |