Chronology of Events
|
|
||||
|
|
||||||
|
|
■ Denver selected to host the DNC August 25 to 28, 2008
■ Venue was selected to be the Pepsi Center for all events including the Acceptance Speech
■ Monthly coordination planning meetings conducted
■ Table top exercises held
■ Venue Changed to INVESCO Field around the week of July 14, 2008
■ Threat Level assessed and determined that Interstate 25 should close around the week of July 28
■ Agencies began to discuss a new plan for security around INVESCO and confirmed I-25 should close in August
■ DNC Acceptance Speech, August 28th, I-25 Closed
|
|
||||
|
|
||||||
![]()
|
Denver Selected to Host
the DNC |
||
|
|
||
|
||
![]() |
||
|
|
||
![]()
|
|
||||||
|
|
Agencies Included
|
|
||||
|
|
||||||
|
|
■ City and County of Denver
■ Multiple Police Agencies involved
■ Multiple EMS and Fire Agencies
■ Multiple State Agencies
■ Multiple Federal Agencies
■ Others
|
![]() |
||||
|
|
||||||
|
|
||||||
![]()
|
|
||||
|
|
Venue Selected
|
|
||
|
|
||||
![]() |
||||
|
|
||||
![]()
|
|
||||||
|
|
Planning for closures, parades, protests, communications, etc
|
|
||||
|
|
||||||
|
|
-Incident Planning Exercises (SEOC, MACC, EMT, others) -Parade/Protest Routes
- Interstate Ramp Closures into Downtown Denver -Communications Plan/DTR Radio Distribution (Interoperability) -DNC Celebrations
-Monthly Debriefings and Intelligence Debriefings
-Pedestrian Traffic/Handicap traffic
-Shuttle Routes/Delegate Routes
-Protocols for CCTV's, VMS's, incidents, tows, decon, etc.\
-Basic Framework for the event was set
|
|
||||
|
|
||||||
![]()
|
|
||||
|
|
Planning for closures, parades, protests, communications, etc
-Hazardous Materials Re-routing
|
|
||
|
|
||||
![]() |
||||
|
|
||||
![]()
|
|
||||
|
|
Venue Changed to INVESCO Field about 30 Days before the conventions
|
|
||
|
|
||||
![]() |
||||
|
|
||||
![]()
|
|
||||||||
|
|
Shifting Gears: (30 Days
to go)
|
|
||||||
|
|
||||||||
|
|
||||||||
|
|
||||||||
|
|
■ Inform Management and FHWA that 1-25 may need to close during rush hour (ADT of 250,000 vehicles )
|
|
||||||
|
|
||||||||
|
|
||||||||
|
|
||||||||
|
|
■ Meetings held with other agencies to collect information such as:
- Time of Closure
- Extent of closure (blast zone perimeter)
- Barricade plans for interstate
- Number of visitors planning at INVESCO
- Delegate Route
- Parking Plan for Convention
- Shuttle Routes/Pedestrian access to convention
- Variable Message and Public Relations Plan
- Redo the last 11 months of work in three weeks....
|
|
||||||
|
|
||||||||
![]()
|
|
||||
|
|
I-25 Peak Hour Traffic Volumes
|
|
||
|
|
||||
![]() |
||||
|
|
||||
![]()
|
|
||||
|
|
Sample PR Egress Plan
|
|
||
|
|
||||
![]() |
||||
|
|
||||
![]()
|
|
||||
|
|
I-25 Closure Points
|
|
||
|
|
||||
![]() |
||||
|
|
||||
![]()
|
|
||||||
|
|
I-25 Closure Thursday Aug 28, 2008
|
|
||||
|
|
||||||
|
|
■ Time Line
- Set the first cone at 5:30PM on 1-70,1-25 and US6
-Detailed MHT's and each ramp manned with police and maintenance personnel
- Last car exited the interstate at about 6:00PM (we planned for 1 hour)
- Traffic was very light no queues formed on I-70 and I-25
(good PR)
- No accidents and breakdowns
- Loaded plows placed on the road
- Secret Service swept the area at about 6:30 to 7:00pm
|
|
||||
|
|
||||||
![]()
|
|
||
![]() |
||
|
|
||
![]()
|
|
||
![]() |
||
|
|
||
![]()
|
|
||
![]() |
||
|
|
||
![]()
|
|
||||||
|
|
Multiple EOC's stood up
|
|
||||
|
|
||||||
|
|
■State Emergency Operations Center
■ Multi Agency Coordination Center
■ Denver Traffic Operations Center
■ Joint information Center
■ Others including backup facilities
|
|
||||
|
|
||||||
![]()
|
|
||||
|
EOC's, Staffing and IMPs
|
||||
|
|
||||
|
|
■ Multijurisdictional EOCs
■ 24/7 staff for the event
■ IMP's developed by agencies
■ EOC Leaders
■ Incident Boards for Tracking
■ Video Surveillance
■ Expect the unexpected (fiber cut, manhole lid, other)
■ Decision makers at the centers empowered
■ Etc.
|
|
||
|
|
||||
![]()
|
|
||||
|
Lessons Learned
|
||||
|
|
||||
|
|
■ Be flexible special events are dynamic
■ Track time and finances
■ Keep a diary (documentation)
■ Know your counterparts in your sister agencies and cities and counties
■ Partnerships are invaluable with other agencies
■ Provide management updates
■ Have written procedures and protocols
■ Confirm information flow before you accept it as fact
■ Conduct Training and table top exercises (test your plans)
■ Follow up on issues they don't go away
|
|
||
|
|
||||
![]()
|
|
||||
|
|
■Questions?
|
|
||
|
|
||||